TIPS - Avoid Putting Dates and Duration of Tasks in the Beginning

Purpose: Dates are automatically calculated by MSP if the task relationships are properly defined.

You should not even think about the dates, duration estimates, or any other task attributes before creating a list of tasks. You should first create the overall structure of project tasks and relationships among them before thinking about durations and dates.